TRENTON FRANKLIN ROAD CLOSING

Only one culvert will be closed at a time. Crews will begin at the southernmost culvert and work north. Length of time for each culvert may vary so dates listed below are estimates only. Details are as follows:

• First culvert -- Located 0.2 mile north of Howe Road and 1.3 miles south of Leichty Avenue. Closing: April 27, 2015. Approximate opening date: May 4, 2015.
• Second, Third, and Fourth culverts -- Located 1.4 miles north of Howe Road and 250 feet south of Leichty Avenue. Approximate closing date: May 4, 2015. Approximate opening date: May 22, 2015.

Detour: Northbound Trenton Franklin Road traffic will detour west on Howe Road, north on Elk Creek Road, and east on Ohio 122. Southbound traffic will reverse this route.

Motorists are encouraged to check the BCEO web site as the best source for possible date and status changes concerning this closure – www.bceo.org/roadclosings .